Karachi [Pakistan] December 28, (ANI): The slow progress and extensive excavation required to prevent damage to an underground main water line on the already delayed Karimabad underpass project have not only increased hardships for the public but have also led to a rise in the project cost from Pakistani Rupees (PKR) 1.4 billion to PKR 3.8 billion, Dawn reported.