JAKARTA, Nov. 5 (Xinhua) — A trial section of the Jakarta-Bandung High-Speed Railway in Indonesia has been ready for operating the EMU (Electric Multiple Units) trains after its traction substation and other equipment have been installed and commissioned on Saturday.
The 14-km-long test track is located between Tegalluar Station and Casting Yard No. 4. and the trial operation for an EMU train is scheduled to be